BISBEE, Ariz. — Arizona Attorney General Kris Mayes urged Cochise County planning commissioners Nov. 19 to delay their Dec. 9 vote on a proposed SpaceX data center.

Mayes asked the commission to wait for state and federal reviews of the project’s potential effects on power reliability, groundwater and public safety.

Tombstone Resources LLC seeks a special use permit for the 747-acre campus along U.S. Highway 191 near the Apache Generating Station.

The proposal calls for up to nine computing buildings and battery storage across four construction phases, according to the county’s hearing notice.

Mayes said the campus would initially require 1.5 gigawatts of electricity.

At full buildout, demand could reach 6 gigawatts, nearly one-fifth of Arizona’s generating capacity based on 2024 federal data.

“Whether residents support or oppose this project, they deserve a meaningful opportunity to be heard and SpaceX must be transparent with the people of Cochise County about its plans,” said Mayes.

The application estimates the campus would use seven to 10 acre-feet of water annually, Mayes wrote.

However, she said water that may be needed to generate electricity for the site was excluded from that estimate.

Additionally, Mayes raised concerns about emergency response outside a fire district, heavy truck traffic, wildlife near Willcox Playa and possible interference with military testing.

“Approving a project of this scale before critical questions have been answered would be premature,” Mayes said.

“Residents deserve transparency, independent analysis, and a full understanding of the project’s impacts before any final decision is made.”

Mayes will take public input Thursday, Dec. 3, from 5:30 to 7 p.m. at the Cochise Elementary School gym, 5025 N. Bowie Ave. Residents can RSVP for the town hall.

CommentShare on FacebookLikes are counted per browser. Reader comments are reviewed before publication.

Join the discussion

We encourage respectful civil discourse. Reader comments are reviewed before publication. Read our discussion policy.

Leave a comment

Your email address will not be published. WordPress stores your submission and technical data for moderation. Approved comments and display names are public.

Submission does not guarantee publication.